FABIAN WAY: The £33m bridge Swansea designed ten years ago still has no money to build it

It would bring a new road into SA1, bypassing some of the busiest parts of Fabian Way. The council had a design drawn up, ready “once a funding package is secured”, and is still waiting.

Alastair Isaac
7 Min Read
Aerial view of the red-brick Bay Campus buildings between the beach at Crymlyn Burrows and Fabian Way, with Kilvey Hill beyond
An aerial view of Swansea University's Bay Campus beside Fabian Way (Image: Swansea Bay City Deal)

Rebuilding Baldwin’s Bridge has been in the plans since 2010. There is still no money to do it.

The scheme would also bring a new road into SA1, giving traffic a way round some of the busiest parts of Fabian Way. Swansea Council last put the cost at almost £33m, in 2021.

That is nearly five times the £6.8m Swansea gets this year for all its schemes from the Regional Transport Fund. On Thursday the council admitted the Welsh Government fund cannot stretch to it, telling councillors the money available “is insufficient to deliver major infrastructure projects of this scale”.

Two lanes of traffic on Fabian Way crossing Baldwin’s Bridge, between concrete parapets and crash barriers, with wooded hills in the distance
Fabian Way where it crosses Baldwin’s Bridge (Image: Google Maps)

A new way into SA1, and a link road to Coed Darcy and the M4

Under plans drawn up by the region’s councils, a new bridge would let Langdon Road be extended through to Baldwins Crescent and the A483.

On the Neath Port Talbot side, a further link road behind Amazon would connect with Coed Darcy, and from there with Junction 43 of the M4 and the A465 Heads of the Valleys trunk road. That road has been planned since at least 2010, but only a short stub of it has ever been built.

Baldwin’s Bridge cost: £33m and ‘beyond the financial means of the Council’

The council put the recommended option at £32,910,000 in April 2021, and admitted that was “beyond the financial means of the Council at present”.

Its officers were working with Neath Port Talbot Council on “a combined funding solution”. The same year it bid for £4.66m to build half of a new Southern Link Road south of Fabian Way and start enabling work for the new bridge.

Ten years of design work on the Fabian Way bridge

Back in 2010, the then Welsh Assembly Government flagged the bridge’s “poor junction arrangement” and a structure that “requires heavy maintenance”. Its answer was a new junction with the roads on separate levels.

The stained concrete underside of Baldwin’s Bridge, marked with graffiti, over a narrow road with cycle route signs
Baldwin’s Bridge from below (Image: Google Maps)

Swansea’s cabinet approved £253,000 of Welsh Government Local Transport Fund money for the detailed design six years later. The aim was to bring the scheme “to a position where the infrastructure could be delivered once a funding package is secured”.

More grants followed every year until 2020, paying for options work, a business case, the design and land, the council said in 2021. That May, cabinet approved terms in private to buy the Four Counties property on Fabian Way for the scheme.

By last year, council officers counted it among four “schemes of national impact” across south west Wales, as the regional transport plan was finalised. Those schemes would get enough regional money to keep the design work going, they said, with the money to build them sought elsewhere.

‘Our patience is now wearing a little thin’ with Welsh Government

Cllrs Chris Holley, Sam Bennett and Peter Black had asked whether the council had spoken to the Welsh Government about the bridge in the past year. At Thursday’s full council meeting Cllr Bennett, the Liberal Democrat member for Waterfront, wanted to know why a scheme the council calls “nationally significant” still has no timescale.

He said the last Welsh Government had paid lip service to it, with about £350,000 put up in the early 2000s for a project he understood would cost nearer £10m.

Labour council leader Rob Stewart said Swansea was “somewhat at the behest of Welsh government”, and the new Plaid Cymru government had taken time since May’s Senedd election to review everything.

His frustration showed: “Our patience is now wearing a little thin on this.” It was not a political point, he added, because the council “lobbied the last government hard on this point”.

Making that stretch a trunk road, run by the Welsh Government rather than the council, has also been looked at, he said. He hoped to see the investment come forward “within the very near future, and by that I mean in the next few years”.

Pressed by Cllr Black on where the bridge sits in the queue, he called it “a high priority scheme”. The northern corridor, already submitted to the Welsh Government but sent “back around the loop”, is a significant priority at the moment, he said, but the bridge “remains a key priority for us in Swansea”.

Regional Transport Fund: £24.7m a year for four councils

Paths, interchanges, flood schemes, road safety and electric car chargers are the fund’s everyday business. The £500,000 to widen the Dunvant to Gowerton cycle path came from it.

Across south west Wales the four councils share £24.7m this year, and the region’s joint transport committee admits that is “not sufficient for the region to achieve its ambitions”. The Welsh Government has told it to expect a flat budget next year.

Cabinet member for environment and infrastructure Cllr Andrew Stevens said the council would keep pushing for more regional money, and look to Welsh Government, UK Government and other sources for the rest.

The region’s transport committee meets on Wednesday to look at next year’s programme, with its list of schemes still to be published.

Author

Alastair Isaac

Reporter for Swansea Bay News