PORTHCAWL: Seafront plan revised as 980-home decision slips to 2027

Fifty retirement flats are out and there is more parking in. Councillors, due to vote before Christmas, will now decide next year.

Kit Peters
8 Min Read
Computer-generated aerial view of flat-roofed apartment blocks and rows of houses beside sand dunes, with paths, a pond and a play area between them
How the flats and houses at Sandy Bay would meet the dunesBridgend County Borough Council

The masterplan for Porthcawl’s seafront has been redrawn, and the decision on whether up to 980 homes and an open-air lido can be built there has slipped into next year.

Fifty retirement flats have been taken out and public parking has gone up, in changes made since the town last saw the plan a year ago.

Bridgend County Borough Council has called off next month’s meeting to decide the planning application, and says a new date will be announced early in 2027.

50 retirement flats are out and 150 more parking spaces are in

A 50-unit retirement living scheme at Coney Beach Park has been taken out of the masterplan.

That means less building beside homes at the northern end of Mackworth Road, the council and the Welsh Government say, and more room for play space and parking.

They now propose about 750 public parking spaces, up to 150 more than before, gathered into fewer and larger car parks.

Hillsboro car park would be re-laid out to fit more cars, with a cycle hub. New car parks are planned at Coney Beach, and another beneath buildings at Salt Lake.

Even so, their application accepts there would be “a modest loss of existing public parking”. A park and ride on the edge of the town centre is being worked up for days when big events are on.

Cllr Colin Davies says the 9 December meeting cannot go ahead

Councillors were due to vote at a special meeting of the development control committee on Wednesday 9 December.

Since then, the council says, the organisations it has to consult have sent in more information, and the public must be given time to comment on it.

Cllr Colin Davies, the cabinet member for housing and regeneration, said the delay “will ensure that the process remains fully transparent”.

He added that the committee would be able to “consider all of the relevant information and feedback before they arrive at a decision”.

The council is the applicant, jointly with the Welsh Government, as well as the authority that decides.

At least 35% of the 980 homes would be affordable, the council says

Homes would go at Salt Lake, Coney Beach and Sandy Bay, as a mix of houses and flats.

Aerial impression of new homes and flats behind the dunes at Sandy Bay in Porthcawl, with the beach on the left, a caravan park in the foreground and the town beyond
Sandy Bay from the air, with the new homes between the dunes and the caravans at Trecco Bay (Image: Bridgend County Borough Council)

At least 35% would be affordable, with an ambition to reach 50% and to put local people first.

Bridgend’s development plan earmarks the site for about 1,100 homes, 30% of them affordable.

The number was cut to around 980 a year ago, when building heights were lowered after residents pushed back.

Plan of Porthcawl seafront from the harbour to Trecco Bay showing proposed buildings at Salt Lake, a park and car parks at Coney Beach, rows of homes at Sandy Bay and the dunes, with a numbered key
The revised masterplan, from the harbour and Salt Lake on the left to Sandy Bay on the right (Image: The Urbanists / Bridgend County Borough Council)

Just over two hectares beside Newton Primary School would be kept back for the school to expand. The dunes at Sandy Bay would be kept and extended.

Lido and hotel by the harbour, with flats up to six storeys at Salt Lake

The lido would sit at the southern end of Salt Lake, facing the harbour, inside a courtyard of buildings with parking underneath. A hotel and a gym are planned beside it.

Impression of an open-air pool in a paved courtyard at sunset, with swimmers, café tables and a building signed Porthcawl Lido
How the lido at Salt Lake could look (Image: Bridgend County Borough Council)

Most buildings would be two or three storeys. Those lining the seafront and the larger open spaces would rise to four, and a few at Salt Lake to six.

Computer-generated aerial view of three and four-storey blocks of flats along a promenade and sea wall, with people on the beach and in the water
The blocks planned along the seafront at Salt Lake (Image: Bridgend County Borough Council)

A year ago, funfair rides were promised on the land next to Aldi. The masterplan now sets that land aside for temporary uses, giving a car boot sale, an ice rink and a Christmas market as examples.

Computer-generated street scene with a fruit stall, a busker and café tables between pale timber and stone buildings, with tall grasses and flowers in the foreground
A market stall and café tables on the link from the promenade towards Dock Street (Image: Bridgend County Borough Council)

Near the dunes, a new building would give beach users showers, changing rooms and toilets. A pump track and mini golf are also planned.

Mackworth Road would no longer take traffic into the site

Only one part of the scheme is up for full permission now: a spine road from Eastern Promenade to Sandy Bay.

Mackworth Road would be cut short at the new park, with a turning area. Drivers would reach Coney Beach and Sandy Bay from a new roundabout on New Road.

At Sandy Bay, a stepped sea defence is planned, with seating built in and easier access to the beach.

Flood modelling, sewer overflows and the Wales Coast Path are in the new papers

The reports now out for comment cover drainage across the site, modelling of coastal flooding and noise.

Others deal with foul drainage, with reducing spills from a combined sewer overflow and with a proposed foul storage tank.

There are options for the Wales Coast Path, which would move onto a continuous walking and cycling route along the seafront from Trecco Bay to the Esplanade.

Anyone who wants to read them, or comment, can find them on the council’s planning portal under reference P/26/140/HYB.

Coney Beach is still being cleared for next summer’s pop-ups

None of this stops the demolition already under way at the old Coney Beach funfair, which is going ahead under existing permissions.

The council expects that site to be cleared by the end of March, and wants padel courts, crazy golf and street food there next summer.

The Buccaneer, once due to be knocked down, is being restored.

Author

Kit Peters

Kit Peters is a journalist and the editor of Swansea Bay News, covering Swansea, Neath Port Talbot and Carmarthenshire since 2020.


Discover more from Swansea Bay News

Subscribe to get the latest posts sent to your email.

Share This Article
Follow:
Kit Peters is a journalist and the editor of Swansea Bay News, covering Swansea, Neath Port Talbot and Carmarthenshire since 2020.
Leave a Comment

Leave a Reply