SCHOOL DELAY: Council asks for six-year delay on new Garden Village school promised with 750-home estate

Families are already moving in. The school they were sold is on a timetable that would surprise most of them.

Alastair Isaac
4 Min Read
Five people in hi-vis vests and hard hats stand outside a new red brick and dark-clad house at the Garden Village development
Left to right: Stuart Phillips of Persimmon Homes West Wales, Cllr Andrea Harrington, Cllr Andrew Williams, Jill Goddard of Swansea Council's housing department, and Ryan Greaney of Persimmon Homes West Wales (Image: Persimmon Homes)

Buy a house on the new estate north of Garden Village and the brochure comes with a primary school. Your children will have left primary school before it opens.

Swansea Council goes to its own planning committee on Tuesday to ask for six more years on the school. It wants the deadline for the plans moved from this December to December 2032.

That is the plans. Building comes after.

A school that arrives with the 201st house

The school was part of the deal when Persimmon got permission for up to 750 homes at Cwrt y Brenin and Llys Pentre in 2019. The developer hands over the land and £5.5m, and the council builds a 2.5-form-entry primary with playing fields.

The catch is in the small print. Persimmon paid a first £266,503 in July 2024. The other £5,233,497 is not due until someone moves into the 201st house.

Nearly seven years after permission, around 65 homes are occupied.

Aerial map view of Persimmon's Garden Village housing development near Gorseinon under construction
The estate north of Garden Village, where up to 750 homes are planned and the school site sits empty (Image: Google Maps)

“Approximately summer 2030”

The council’s education department says it cannot start designing the school until the rest of the money lands, and on Persimmon’s current pace the 201st house is “approximately summer 2030”.

From there its timetable runs: cash in autumn 2030, first sketches autumn 2030, detailed design spring 2032, planning application autumn 2032. Officers want a condition that building starts within two years of that.

The one bit of the school already finished is the drop-off zone. It was built with the first phase of houses.

Why the houses are slow

Officers put the pace down to “some delays in the delivery of dwellings” and the Burry Inlet nitrates problem, the estuary pollution rules that have held up housing across everything draining to the Gowerton treatment works.

The school itself dodges that issue. The rules let a school serving children whose homes already drain to the estuary be waved through.

The council bought all 141 affordable homes on the estate from Persimmon in August, 70 of them for families on the housing waiting list. The press release that day said the wider scheme “also includes a primary school”.

8,000 empty desks by the time it’s designed

By 2032 the council’s own forecasts say Swansea will have 8,000 empty primary places, more than one in three. Those forecasts leave out children from new housing, which is what Garden Village is.

The papers going to committee do not say which schools the estate’s children are using in the meantime.

No residents responded to the notices, Llwchwr Town Council has no objection, and officers recommend approval. Councillors decide online at 2pm on Tuesday.

Related stories from Swansea Bay News

GARDEN VILLAGE: Council buys 141 homes at new estate, 70 for the housing waiting list
The August deal that mentioned the school in passing.

SWANSEA: Falling birth rate to leave 8,000 primary school desks empty by 2032
The forecasts that leave new housing out.

GORSEINON: Up to 400 homes planned for former 3M factory site
The next scheme in the queue on Gorseinon Road.

More Persimmon Homes coverage from Swansea Bay News
Every story on the developer’s Swansea sites.

Author

Alastair Isaac

Reporter for Swansea Bay News

Share This Article
Reporter for Swansea Bay News
Leave a Comment

Leave a Reply